Q1 2024 Quarterly Report

Q1 2024 Quarterly Report

Quarter Highlights

Managing Director Ivan Fairhall said: “Having joined Pivotal Metals in September, I’m very pleased to present my first full Quarterly Report which outlines significant progress on all aspects of our exploration endeavours.

The importance of drilling at Horden Lake cannot be understated. We have a clear strategy to add value to the asset de-risk and show the growth potential of this already significant 412kt CuEq indicated and inferred Cu-Ni-PGM resource. Investors will now benefit from considerable newsflow off the back of work completed to date. We are also highly enthused by the BAGB results which fully support our geological model and provide exciting targets of scale for future drilling.

With a cash boost late last year, clean balance sheet, and two very exciting exploration and development projects, the Board and I are looking forward to delivering a full operational and news schedule to all shareholders over the coming months.”

OPERATIONAL UPDATE

HORDEN LAKE PROJECT

In March 20241, Pivotal Metals announced the completion of the drilling program at Horden Lake in Quebec, the first drilling by Pivotal at Horden Lake since its acquisition. The completed program includes 33 holes for a total of 7,014 meters of diamond drilling. This effort targeted both grade and tonnage opportunities within the existing 412 kt CuEq (27.8mt at 1.5% CuEq) Indicated and Inferred Resource, aiming to further delineate and expand the mineral resource base.

The program was designed to target improvements to both the quality and scale of the Horden Lake project and provide the foundation for advancing the asset from both a geological and an engineering perspective.

Drill core is being progressively logged by the geological team in Val d’Or and sent for multielement assay with ALS Global. Results are expected during the 2nd quarter.

It is noted the winter program included establishment of a new seasonal access road linking directly to Billy Diamond national highway, 10km to the east of the project. This road is now in place for future programs, and importantly greatly lengthens the winter drilling window by enabling property access from early December, vs late January achieved this year.

source