Key Safety Permit Received for China Battery Grade Manganese Sulphate Plant

Key Safety Permit Received for China Battery Grade Manganese Sulphate Plant

HIGHLIGHTS

Cautionary Statement

The Feasibility Study referred to in this announcement is a Technical Feasibility of the establishment of the Battery Grade Manganese Sulphate Plant Stage 1 Processing Plant in China (the Plant). Please refer to ASX announcement dated 7/5/24 for full Feasibility Study details.

The Feasibility Study is based on the material assumptions contained in the Feasibility Study document which accompanied the announcement. This announcement and the Feasibility Study include assumptions about the availability of funding. While the Company considers all the material assumptions to be based on reasonable grounds, there is no certainty that they will prove to be correct or that the range of outcomes indicated will be achieved.

Notwithstanding the Finance Update as set out in the ASX announcement dated 14/5/24, investors should note that there is no certainty that the Company will be able to raise the amount of funding to develop the Plant when needed. It is also possible that such funding may only be available on terms that may be dilutive to or otherwise affect the value of Company’s existing shares.

It is also possible that the Company could pursue other ‘value realisation’ strategies such as a sale, partial sale or joint venture of the Plant. If it does, this could materially reduce the Company’s proportionate ownership of the Plant. Given the uncertainties involved, investors should not make any investment decisions based solely on the results of the Feasibility Study.

In China there are total of 8 major permits required for construction and operation, which are outlined below, along with status updates for each permit:

These permit applications can proceed concurrently with Feasibility Studies, engineering assessments, and financing endeavours, with the critical permits being environmental, safety & energy permits.

Once all key permits are obtained, with the expectation that the remaining two permits will be received before the end of the financial year and following the anticipated Final Investment Decision in the second half of 2024, Firebird will be ready to immediately begin construction on its battery-grade manganese sulphate plant.

Construction is projected to take only 12-15 months, with operations expected to commence in late 2025.

Firebird Managing Director Mr Peter Allen commented: “As we continue to efficiently advance the necessary permits for our battery grade manganese sulphate plant, I am pleased to announce that we have received the first of three critical permits, being the safety permit, and expect the remaining two permits to be received by the end of June.

“We are moving at a rapid pace on-the-ground in China and that is due to the hard work of our leading manganese team and the strong level of in-country support we have and continue to receive. Importantly, we continue to tick all the boxes in the delivery of our high-purity manganese sulphate strategy and have defined a low-cost, near-term pathway to production. We expect to make a Final Investment Decision in the second half of 2024, immediately commence construction activities and work extremely hard towards commencing operations in late 2025.”

source