Stage 1 of BHP's Jansen Potash Project Hits Halfway Mark

Stage 1 of BHP's Jansen Potash Project Hits Halfway Mark

“As JS1 crosses the halfway mark, the focus now shifts towards the completion of the mill building and processing plant, port construction, finalizing infrastructure and gearing up to handover the project to operations,” the company stated in the press release.

Stage one has a planned annual production of 4.15 million tonnes, with first production expected to be delivered in late 2026. Stage two construction is anticipated to take six years, with its first production in 2029 followed by a ramp-up period of three years.

Once both stages are complete, the project is designed to produce approximately 8.5 million tonnes per annum of agricultural-grade potash.

“Building one of the largest potash mines in the world requires an all-hands-on-deck approach, and the province has really come together to make a project of this magnitude possible,” said Karina Gistelinck, BHP’s asset president for potash. “Delivering Jansen safely remains our top priority as we get ready for Jansen operations in 2026.”

The project is expected to operate for up to 100 years, and once stage 2 is complete, Jansen is expected to supply about 10 percent of global potash production.