Home » Lithium Brine Supply Agreement Signed with Electroflow

Lithium Brine Supply Agreement Signed with Electroflow

Lithium Brine Supply Agreement Signed with Electroflow

Highlights

‘In May 2024, using Mandrake’s Utah Lithium Project brines, Electroflow achieved outstanding repeatable lithium recoveries of 92% and conversion to lithium hydroxide with no chemical pre-treatment.

Mandrake will now be trucking a large quantity of Utah Lithium Project brine to Electroflow’s pilot plant which will provide important information on recovery and purity of lithium hydroxide produced on an ongoing basis at a larger scale. Crucial commercial information relating to costs of processing will also be delivered.

In a difficult environment for lithium players, Mandrake has been able to make impressive headway with the Utah Lithium Project without compromising the Company’s cash position. The successful qualification for US$1M of US Federal DoE funding, commitment from two DLE providers to build pilot facilities at their own cost and Mineral Resources Estimate due this quarter has the Company well positioned going forward.’

Key terms of the LBSA include:

To ensure costs remain low, Mandrake will re-enter previously sampled legacy oil and gas wells in order to generate adequate volumes of brines for Electroflow’s pilot plant facility. Mandrake will initially truck a large volume of brine to Electroflow’s existing San Francisco Bay Area laboratory facility to enable preliminary processing to calibrate equipment and finalise pilot plant design.

The bulk of the pilot plant processing work will then commence in Utah early in the new year. The projected scale of production from the pilot plant facility is anticipated to be several hundred grams of high purity lithium hydroxide per day.

The successful completion of pilot plant DLE work on Utah Lithium Project brines will provide crucial information on the potential commerciality of processing Mandrake brines.

Mandrake is on-track to deliver a Mineral Resource Estimate (MRE) for the Utah Lithium Project during the current quarter. The MRE will be followed by the commencement of a scoping study.

source