Tartana Makes Significant Strides at Copper Sulphate Plant with Recent Shipment Totalling 150 Tonnes

Tartana Makes Significant Strides at Copper Sulphate Plant with Recent Shipment Totalling 150 Tonnes

Highlights:

Tartana Minerals Managing Director, Stephen Bartrop, commented:

“This shipment marks an important milestone as it represents our largest shipment to-date within the Company’s recent sales to the North Australian mining industry. Improved plant performance has led to increased product quality and which is continuing to build a strong market for our ongoing copper sulphate pentahydrate production.”

Plant Production and Ongoing Activities

Production for the Company’s next shipment, targeted to be approximately 70 tonnes, is well advanced with approximately half the shipment completed and in storage with the remainder to be produced next week.

Plant production is ongoing with a significant improvement in plant reliability and copper sulphate pentahydrate quality which utilises Tartana’s proprietary process for creating free flowing crystal with low levels of impurities.

Ongoing exploration and metallurgical work to support future Copper Sulphate production

As reported in the June Quarterly Report (reported on the 31 July 2024) drilling of metallurgical hole D15 has been completed to a total depth of 300.8 m. This metallurgical hole is providing primary copper mineralisation samples for metallurgical testwork including flotation recoveries, potential concentrate grades and ore sorting. The results of this testwork and the core assaying are well advanced with the results expected shortly.